The Senegalese government's Structural Support Project for the Digital Land-Use Strategy, known as PASSANT, has been embroiled in controversy since its inception in 2019. The project, awarded to Spanish firm Liteyca through an unsolicited bid, aimed to develop a fibre-optic network across the country. The project was allocated CFA 50,000,838,369, including taxes, and was expected to be completed within 24 months. However, the project has faced significant delays and irregularities, leading to the dismissal of three SENUM SA managers.

An audit report by the Public Procurement Regulatory Authority (ARCOP) revealed that the project was "broadly consistent with the studies" but noted a 22-month delay, stalled work, and a lack of rigour on the part of SENUM SA. The report also highlighted management fees of CFA 4,513,438,738 paid without guarantees, late-delivery penalties of around CFA 5 billion not applied, and work outside the estimate worth CFA 69 million. The auditors described the execution as "unsatisfactory" and recommended a detailed study.

SENUM SA's management has linked the dismissals of the three managers to the findings of the ARCOP report and a second, unpublished audit that reportedly estimated losses of CFA 24 billion. The company accuses the dismissed employees of gross misconduct, including failure to exercise contractual rights and overpricing of civil engineering work. However, the employees and the Réseau des Sénégalais pour le numérique et la souveraineté informatique (RNS) collective dispute the allegations, claiming the dismissals were irregular and that they were not given sufficient opportunity to respond.

The RNS collective has accused SENUM SA's managing director, Isidore Diouf, of refusing to reinstate the dismissed employees, despite requests from the supervising ministry. The collective claims that the managing director has taken a hardline stance, while SENUM SA's management maintains that the dismissals were justified and in line with labour law. The dispute has highlighted tensions between the company's management and employees.

The PASSANT project was initially expected to be completed within 24 months, but its deadline was extended twice, first by 18 months in January 2021 and then by 15 months in January 2023. The project's current status remains unclear, with the ARCOP report noting that work had "stopped" and there had been no provisional acceptance. The project's delays and irregularities have raised concerns about its viability and the value for money.

The Senegalese government's PASSANT project was intended to develop a fibre-optic network across the country, including 339.8 km of backbone network, fibre connections for over 300 government buildings, and 125 public Wi-Fi points. However, the project's progress has been slow, and its completion remains uncertain. The dispute between SENUM SA's management and employees has added to the project's woes.

The controversy surrounding the PASSANT project has raised questions about the management of large-scale IT projects in Senegal. The project's delays, irregularities, and disputes have highlighted the need for greater transparency and accountability in the management of public funds. The outcome of the dispute and the project's future remain to be seen.

Key points

  • The PASSANT project's delays and irregularities have resulted in significant financial losses, estimated at CFA 24 billion by SENUM SA.
  • The dispute between SENUM SA's management and employees has highlighted tensions between the company's leadership and staff.
  • The project's future and its potential to achieve its intended goals remain uncertain.