On November 22, ION News published an article highlighting concerns over the Tamarind Falls project, citing a lack of pipes and fittings. The article reported that the Minister had expressed disappointment to the Central Water Authority's (CWA) General Manager, saying "You have failed!" In response, CWA General Manager Shyam Thanoo addressed the issue on a radio show, providing context and explanations for the project's delays.

According to Thanoo, the CWA had faced challenges with procurement and supplier delivery times. The project's commissioning timeline was initially set at one month but was accelerated to 15 days, with a target of 10 kilometers of piping. However, Thanoo acknowledged that the CWA had faced difficulties in meeting this target due to factors beyond their control, including delays in receiving necessary parts.

Thanoo emphasized that the CWA had worked to achieve the accelerated commissioning date, but unfortunately, suppliers were unable to meet the required timeline. As a result, the CWA had to rely on private sector assistance to complete the project. Despite these challenges, Thanoo expressed a positive outlook, stating that the CWA had taken the criticism constructively and was committed to meeting its targets.

The Tamarind Falls project aims to alleviate the water crisis in Mauritius, which has been ongoing for several months. The crisis has been exacerbated by recent social unrest and supply chain disruptions. Thanoo's comments highlight the complexities and challenges faced by the CWA in delivering this critical project.

ION News had previously reported on the concerns surrounding the Tamarind Falls project, citing sources that suggested the Minister's dissatisfaction with the project's progress. Thanoo's public response demonstrates a commitment to transparency and accountability, acknowledging the project's delays and outlining the efforts made to address them.

The CWA's efforts to address the water crisis in Mauritius have been hampered by supply chain issues and delays. Thanoo's comments underscore the importance of cooperation and collaboration in delivering critical infrastructure projects. The CWA's commitment to completing the Tamarind Falls project is crucial in alleviating the water crisis affecting the island.

ION News welcomes Shyam Thanoo's transparency and accountability in addressing the Tamarind Falls project delays. The publication encourages open dialogue and constructive criticism, recognizing that this approach is essential in ensuring that public authorities are held accountable for their actions. By engaging in public debate, Thanoo has demonstrated a commitment to responsible leadership and governance.

Key points

  • CWA General Manager Shyam Thanoo addresses Tamarind Falls project delays, citing supply chain issues and accelerated commissioning timeline.