The Ugandan Ministry of Water and Environment has released documents that provide a different account of the controversial Kanoni water project in Kazo and the Shs20.158bn Nyabuhikye-Kikyenkye water supply scheme in Ibanda. These documents raise questions about the figures quoted during Minister Balaam Barugahara's inspections, the actual scope of the projects, their implementation timelines, funding arrangements, beneficiary payments, and the number of households that have received water.
The Ministry's records suggest that some of the information presented to Minister Barugahara may not have captured the full project history and implementation status. In Kazo, the Minister reportedly found that the Kanoni Sub-County water project had remained stalled for eight years after being commissioned by President Yoweri Museveni. He also raised concerns about the Shs20bn Kicence-Keihangara-Igorora water supply scheme, which residents reportedly said had been completed in 2021, yet households were still struggling to access water.
An audit report cited during the investigations established that more than 400 residents had each paid Shs100,000 through Centenary Bank for water connections but had neither received the service nor been refunded. However, the Ministry's records now reveal additional information about the two projects, including the actual cost of the Kanoni reservoir, the phased implementation arrangements, and the reasons given for the delays.
One of the biggest disagreements concerns the amount reportedly spent on the Kanoni water project. The Ministry put the cost of constructing the Kanoni reservoir, including site works, at Shs579,678,500. This is substantially different from the Shs20bn figure reportedly cited during the Minister's investigations. The Ministry explained that the remaining distribution mains, system intensification, and augmentation works were planned under Phase II, which was dependent on securing additional funding.
The Ibanda project has an even more complicated history. According to Ministry of Water records, the Nyabuhikye-Kikyenkye Gravity Flow Scheme was contracted to Block Technical Services Limited, with M&E Associates Limited serving as project management consultants. The contract was signed on April 15, 2017, with construction commencing on July 6, 2017. The original completion date was October 6, 2018, but the project experienced significant delays.
Perhaps the most sensitive issue concerns the money collected from residents who wanted household water connections. Approximately 860 beneficiaries had paid Shs100,000 each as their contribution towards household connections. However, only approximately 450 connections had been completed, leaving about 410 paid-up beneficiaries without access to the service. The district requested the Ministry to provide an updated project status, identify outstanding works, and explain arrangements for connecting all beneficiaries who had already paid.
The Ministry's subsequent response provided further details. It said approximately 450 first-batch promotional household connections involving 860 people who paid Shs100,000 each were completed. The Ministry's records suggest that some beneficiaries received the services promised, but concerns remain about the usage of public funds and the number of households that have received water. The documents do not automatically clear anyone of responsibility but provide additional leads that investigators must examine.
Key points
- The Ministry of Water and Environment disputes the suggestion that Shs20bn was spent on constructing the Kanoni tank, citing a cost of Shs579,678,500 for the reservoir and site works.
- Approximately 410 paid-up beneficiaries remain without access to water connections in the Ibanda project.
- The Ibanda project experienced significant delays due to disputes involving landlords and sections of the community.