The Nyanzaga Gold Project, located in Sengerema District, Mwanza Region, has participated in the Seventh Tanzania Mining and Investment Conference (TMIC 2026) as a new investor preparing to join Tanzania's gold-producing sector. The project, being developed by Sotta Mining Corporation Limited, a joint venture between Perseus Mining and the Government of Tanzania, has been 17 years in the making. With first gold pour targeted for January 2027, the project is expected to become Perseus Mining's fourth gold mine in Africa.
Perseus Mining acquired the project in 2024 and made its Final Investment Decision in April 2025. Since then, the project has made significant progress, including connection to the national electricity grid and securing water supply from Lake Victoria. The project has also handed over houses to families relocated to pave the way for the project and advanced construction of its processing plant. These developments demonstrate the project's readiness to commence production.
The Nyanzaga project has generated a direct economic contribution of 457.7bn/- to Tanzania between July 2024 and March 2026. This includes 371.6bn/- spent on local suppliers and 60.7bn/- paid to the government. The project has also created employment opportunities, with over 3,600 people currently working at the project site, including 281 direct employees, the majority of whom are Tanzanians.
In addition to its economic contributions, the project has provided 202 training opportunities, community water infrastructure, a replacement primary school, and a new dispensary. The company has worked closely with the Ministry of Minerals, the Mining Commission, and other regulatory institutions, while participating in industry platforms, including previous editions of TMIC.
Country Manager Isaac Lupokela stated that the company participated in TMIC as a key stakeholder in the mining sector as it prepares to commence production. He noted that Nyanzaga has been under development for 17 years and that the first gold pour will demonstrate that Tanzania's mineral resources remain viable and beneficial to the nation.
The Nyanzaga project is expected to produce an average of more than 200,000 ounces of gold annually from the 2028 to 2035 financial years. This will make it a significant contributor to Tanzania's gold production and a major player in the country's mining sector. The project's progress and expected production have been welcomed by stakeholders, who see it as a boost to the country's economy.
As the project nears its first gold pour, it is expected to have a positive impact on the local community and the Tanzanian economy as a whole. With its significant economic contributions, job creation, and infrastructure development, the Nyanzaga project is poised to become a major success story in Tanzania's mining sector.
Key points
- The Nyanzaga Gold Project is expected to produce an average of more than 200,000 ounces of gold annually from 2028 to 2035.