The Mauritius Land Drainage Authority has announced that 625 kilometers of drains and 111 kilometers of rivers have been cleaned in preparation for the 2026-2027 rainy season. This effort aims to mitigate the risk of flooding and ensure smooth water evacuation. The authority has also planned new inspections and maintenance works to be completed before December. A public meeting was held on September 24 at the Port-Louis municipality to coordinate efforts.

The meeting brought together concerned ministers, local authorities, police, the Land Drainage Authority, and the National Disaster Risk Reduction and Management Centre. The next step involves re-inspecting drains, rivers, roads, and other infrastructure that could impact water evacuation. Additional works identified during these inspections are expected to be completed before December. The distances announced demonstrate the scale of maintenance carried out.

A public map will be published to show the cleaned sections, obstacles discovered, remaining works, and the administration responsible for each intervention. This transparency aims to keep the public informed about the progress and challenges in flood prevention. The map will help residents track the maintenance work in their areas.

According to information shared during the meeting, the budget allocated for cleaning has been reduced from Rs 222 million to Rs 125 million. The reduction was partly due to some local authorities not utilizing their funds during the previous exercise. This development raises questions about potential delays in work and the impact on vulnerable areas.

The effectiveness of the cleaning efforts cannot be solely evaluated based on the total kilometers cleaned. The impact of wild deposits, uncontrolled construction, and works obstructing water flows can quickly negate the progress made. Therefore, preparation must be assessed neighborhood by neighborhood.

The Land Drainage Authority's efforts are crucial in preventing flooding and ensuring public safety. However, the reduction in budget and potential delays in work may affect the overall outcome. The public must be kept informed about the challenges and progress in flood prevention.

The authority's proactive approach and public engagement are essential in addressing the concerns of the residents. The upcoming inspections and maintenance works will help identify areas that still require attention. The public map will facilitate a better understanding of the efforts being made to prepare for the rainy season.

Key points

  • 625km of drains and 111km of rivers have been cleaned in Mauritius ahead of the 2026-2027 rainy season.
  • A public map will be published to show the cleaned sections, obstacles discovered, and remaining works.
  • The budget for cleaning has been reduced from Rs 222 million to Rs 125 million.

Share this story

Written by

SaharaWire Newsroom
SaharaWire

Reporting for SaharaWire from the Nairobi bureau.