Mauritania's national electricity company, Somlec, has canceled its contracts with CTM, a construction company owned by a deputy in the country's parliament. The decision was made after a thorough investigation into recent fires at Somlec's power plants, which found CTM responsible for contractual breaches. Somlec's management informed CTM's director, Mustafa Mohamed El Muktar, of the cancellation in a letter dated November 12.

The canceled contract, numbered 01/CMI/2026, was awarded on January 22, 2026, and involved the construction of two new power plants in Nouakchott and the rehabilitation of six existing ones. The contract was signed with a consortium led by CTM, which included Turnkey Solution SARL and Electromechanical & Communication Engineers. Somlec cited multiple instances of CTM's failure to meet contractual obligations, including delays in project implementation and a lack of adherence to agreed-upon specifications.

According to Somlec, CTM's failures included inadequate preparation and submission of execution studies, significant delays in project progress, and an inability to respect the contractual deadline. As of October 15, 2026, the actual progress of the work was only 3.5%, despite 27% of the contractual deadline having passed. Somlec also noted that CTM had not respected commitments related to key personnel, with the project manager, Abdullah Ould Al-Tayyeb, leaving the project without prior notice.

Somlec's decision to cancel the contract was also influenced by a report from the investigation committee on the fires at Somlec's power plants. The report held CTM and the engineering consultant, IRAF, responsible for the fires, citing the use of non-compliant documents and the failure to conduct necessary tests on the installed cables. The report also noted that CTM had exceeded the contractual deadline and failed to renew insurance policies for the construction site.

In addition to the contractual breaches, Somlec expressed concerns about the quality of work and the lack of transparency in CTM's operations. The company noted that CTM had not provided a plan for replacing the project manager or addressing the issues raised by Somlec. Somlec's management emphasized that the cancellation of the contract does not absolve CTM of its contractual and financial obligations.

The investigation committee's report also identified shortcomings in CTM's organization, coordination, and monitoring of the project. Somlec stressed that these issues demonstrate a persistent lack of capacity and commitment from CTM to fulfill its contractual obligations. The company's decision to cancel the contract aims to protect Somlec's interests and seek compensation for damages resulting from CTM's failures.

Somlec's move to cancel the contract with CTM reflects the company's efforts to address the challenges facing its power infrastructure and ensure the reliable provision of electricity to the Mauritanian people. The cancellation also highlights the need for greater accountability and transparency in public procurement and contracting in Mauritania. Key points include Somlec's assertion of CTM's contractual breaches, the investigation committee's findings on the causes of the fires, and the potential financial and reputational implications for CTM.

Key points

  • Somlec's cancellation of the contract with CTM cites persistent and substantial failures to meet contractual obligations.
  • The investigation committee's report holds CTM responsible for the recent fires at Somlec's power plants.
  • The cancellation of the contract aims to protect Somlec's interests and seek compensation for damages resulting from CTM's failures.