Kenya has entered a new phase in crude oil production as Gulf Energy E&P BV SEZ began drilling at the Amosing 1 well in the South Lokichar Basin of Turkana County. The drilling ceremony was presided over by Energy and Petroleum Cabinet Secretary Opiyo Wandayi. This marks a significant milestone in Kenya's upstream oil story. The Amosing field is one of four fields covered in the first development phase, collectively known as the NEAT fields.

Gulf Energy E&P BV SEZ is using a GW70 onshore rig leased from China's Great Wall Drilling Company for the drilling operation. The company holds the South Lokichar acreage across Blocks T6 and T7. The project has an estimated 326 million recoverable stock-tank barrels over a 25-year contract period. This reserve gives Kenya a credible upstream base, but execution will be crucial at this stage.

The project targets initial output above 20,000 barrels per day from 1 December 2026. To achieve this, Gulf Energy will initially move crude by road from Turkana to Mombasa, sidestepping the wait for a dedicated export pipeline. However, this arrangement places early pressure on road capacity, logistics planning, and truck turnaround times.

The first export cargo is targeted for March 2027, setting a near-term test for both production and logistics. This project follows Gulf Energy's acquisition of Tullow Oil's Kenyan upstream assets, which transferred operatorship to the current developer. The acquisition marked a significant change in Kenya's upstream oil landscape.

Kenya's entry into commercial oil production is an execution story, with key metrics for investors including well performance data, trucking volumes from Turkana, and the March 2027 export milestone. Road-based logistics carry inherent constraints on scale, and any expansion beyond the initial 20,000 bpd target will require sustained operational consistency and a decision on pipeline infrastructure.

The project has significant implications for investors, who will be watching key metrics such as well performance data and trucking volumes. The December 2026 production figure and the March 2027 cargo date will define market confidence in Kenya's upstream story for years ahead.

Gulf Energy E&P BV SEZ began drilling at the Amosing field on 20 November 2026, marking a major milestone in Kenya's oil production journey. The company aims to achieve first commercial production above 20,000 barrels per day from 1 December 2026.

Key points

  • Kenya targets first commercial oil production above 20,000 barrels per day from 1 December 2026
  • The project has an estimated 326 million recoverable stock-tank barrels over a 25-year contract period
  • The first export cargo is targeted for March 2027, to be transported by road to Mombasa

Reporting sources

Share this story

Written by

SaharaWire Newsroom
SaharaWire

Reporting for SaharaWire from the Nairobi bureau.