The Utility Regulatory Authority (URA) in Mauritius has opened a public consultation process for eleven solar projects with a combined capacity of approximately 80 MW. These projects are awaiting approval before they can inject electricity into the national grid. If approved, they could represent a significant contribution to the country's electricity system, which had a total installed capacity of around 880 MW as of 2024.
The eleven projects are distributed across several regions in Mauritius and include two with battery storage systems. The largest project is Stor'sun 2 Ltd's proposal in Trou-d'Eau-Douce, followed by Avipro Co. Ltd's and Les Moulins De La Concorde Ltée's projects in Amaury. Tianli Spinning (Mauritius) Co. Ltd has submitted two separate projects in Petite-Rivière. If all licenses are granted, the projects could increase the country's solar capacity by over 20%.
The development of these projects comes as the Mauritian government has recently revised its renewable energy targets. On October 28, 2026, Energy Minister Patrick Assirvaden announced that the goal of generating 60% of the country's electricity from renewable sources by 2030 had been pushed back to 2035. This decision was justified by the need for "realistic" objectives, given that the share of renewable energy had decreased from 21% to 17% between 2014 and 2024.
As of October 15, 2026, Mauritius had a total renewable energy capacity of approximately 395 MW, including around 198 MW of solar power. The country's solar capacity is expected to increase with the development of these new projects. For comparison, a 4.2 MW solar farm inaugurated in Arsenal in late October is expected to produce enough electricity for around 4,500 households.
The URA's decision will be crucial for the future of these eleven projects. According to the Electricity Act 2005, anyone wishing to oppose a project can submit a written objection within 14 days of the notice being published. The projects are part of a busy development schedule, with the energy minister announcing the commissioning of ten CNIS (Carbon Neutral Industrial Sector) projects representing around 54 MW by December.
In addition to these projects, four solar projects with battery storage, totaling 60 MW, are currently under construction, with the first expected to be completed in December. The projects awaiting approval include those from Mauritius Freeport Development Company Ltd, Compagnie Mauricienne De Textile LTEE, and RT Knits Ltd, among others.
The eleven projects have a combined capacity of 78.831 MWdc / 57.046 MWac. They are as follows: 1. Mauritius Freeport Development Company Ltd - 3.31 MWdc / 2.5 MWac, 2. Mauritius Freeport Development Company Ltd - 3.63 MWdc / 2.75 MWac, 3. Compagnie Mauricienne De Textile LTEE - 4.411 MWdc / 4.0 MWac, 4. Tianli Spinning (Mauritius) Co. Ltd - 4.011 MWdc / 3.2 MWac, 5. Tianli Spinning (Mauritius) Co. Ltd - 10 MWdc / 4.0 MWac, 6. RT Knits Ltd - 6.0 MWdc / 5.5 MWac, 7. Gamma Materials Ltd - 3.835 MWdc / 3.8 MWac, 8. Gamma Materials Ltd - 3.206 MWdc / 3.2 MWac, 9. Avipro Co. Ltd - 13.87 MWdc / 10 MWac, 10. Les Moulins De La Concorde Ltée - 9.89 MWdc / 8.096 MWac, 11. Stor'sun 2 Ltd - 16.668 MWdc / 10 MWac.
Key points
- The projects could increase Mauritius' solar capacity by over 20% if approved.