The Democratic Republic of Congo's Kamoa-Kakula Copper Complex has begun receiving continuous solar-based power from a 233-megawatt solar photovoltaic plant integrated with a 526-megawatt-hour battery energy storage system. Located near Kolwezi in the country's Copperbelt region, the facility entered commercial operation on 12 August 2026. It is designed to provide the mine with a guaranteed 30 megawatts of baseload electricity around the clock.

The project, owned and operated by CrossBoundary Energy, with Germany's Dhybrid Power Systems providing the battery system engineering and control platform, demonstrates how private investment and energy technology can address the electricity requirements of major industrial facilities. In its first month of operation, the facility displaced approximately four million litres of diesel. This reduction in diesel consumption points to the potential financial and environmental benefits of integrating solar generation with battery storage.

For mining companies, dependable electricity is essential, particularly in energy-intensive activities such as crushing, processing, pumping, and material handling. Interruptions or unreliable supply can affect production schedules, operating costs, and the ability to meet delivery commitments. DR Congo has considerable mineral resources, particularly copper and cobalt, but reliable power remains a constraint on industrial development.

The Kamoa-Kakula installation illustrates how a dedicated renewable energy system can support DR Congo's ambition to build the energy and industrial systems required to process resources more efficiently and retain greater economic value. Solar panels generate electricity during the day, while batteries store excess power for use when sunlight is unavailable. This combination helps provide a more consistent supply than solar generation alone.

The project highlights an investment model that could be relevant to other African mining operations. Rather than relying exclusively on national grid infrastructure, mining companies and independent power producers can develop dedicated energy arrangements through long-term commercial partnerships. Such projects can help address immediate industrial requirements while creating opportunities for renewable energy developers, engineers, equipment suppliers, and technical specialists.

However, the model should not be mistaken for a complete solution to DR Congo's electricity challenges. A private power installation serving one mining complex does not resolve wider national shortages or guarantee electricity access for surrounding communities. Expanding reliable power across the economy will still require investment in public grids, transmission lines, generation capacity, and distribution systems.

The project's performance will ultimately be judged by its ability to deliver dependable electricity, reduce operating costs, and maintain environmental standards. Its wider significance lies in demonstrating that renewable energy can serve demanding industrial operations, not only households and small businesses. As Africa seeks to expand its role in global mineral supply chains, the Kamoa-Kakula experience offers a practical lesson: access to reliable energy is central to turning natural resource wealth into sustainable industrial competitiveness.

Key points

  • The project displaced approximately four million litres of diesel during its first month of operation.
  • The facility provides a guaranteed 30 megawatts of baseload electricity around the clock.
  • The project demonstrates how private investment and energy technology can address the electricity requirements of major industrial facilities.

Reporting sources

Share this story

Written by

SaharaWire Newsroom
SaharaWire