The demolition of constructions and installations on the GMS-Samé-Kati section of the road project began on November 16. This project, valued at over 92.6 billion FCFA, aims to improve traffic flow on one of Bamako's busiest routes. The project involves the demolition of structures and installations on a 9.3-kilometer section of the road, which is part of a larger project that includes 11.481 kilometers of road between Bamako, Koulouba, and Kati.

The project has been in the works since March 2024, when a decree declared the works on the entire section of concern to be of public utility, allowing for the expropriation of private properties. The Malian government has put in place a framework to ensure fair compensation for those affected, with 1,270 dossiers paid out between January 2025 and August 2026, totaling 21.102 billion FCFA.

For the Bamako-Koulouba-Kati, Point G, and Kati road program, which includes the GMS-Samé-Kati section, the total indemnifications amount to 3.148 billion FCFA. As of August 20, nearly 75 million FCFA had been paid out in 2025, and 3.073 billion FCFA in 2026. The government has emphasized that the compensation process is ongoing and that those affected will receive fair and prior compensation.

The main market for the project was approved in May 2024 for 92.662 billion FCFA/TTC and was awarded to COVEC-Mali with a 36-month execution deadline. An additional market for the control and supervision of the works, valued at 1.811 billion FCFA, was awarded to the GTAH/GOPA group for 38 months. The project is being implemented in phases, with the GMS-Samé-Kati section being a crucial part of the overall plan.

The project was officially launched on February 1, 2024, and as of February 26, 2026, the rate of progress was 10% for approximately 33% of the deadline consumed. However, by mid-October, the Direction générale des Routes reported that the works were progressing in line with the projected calendar.

The liberation of the GMS-Samé-Kati section marks a significant milestone in the project, which aims to alleviate traffic congestion and improve road safety in Bamako. The Autorité Nationale de Sécurité Routière (ANASER) has been conducting awareness campaigns along the axis, educating road users, traders, and residents on the importance of road safety and the need to vacate the areas designated for the road expansion.

The project has significant implications for the residents and businesses along the axis, who are already experiencing the effects of the project. The ANASER has been engaging with stakeholders, including traders, garage owners, truck drivers, and school administrators, to ensure a smooth transition and minimize disruptions.

Key points

  • The Malian government has earmarked 3.148 billion FCFA for indemnifications related to the Bamako-Koulouba-Kati road program.
  • The project involves the demolition of constructions and installations on a 9.3-kilometer section of the road.
  • The main market for the project was approved in May 2024 for 92.662 billion FCFA/TTC.