The construction of Morocco's Stade Hassan II in Fès is set to reach a significant milestone by the end of November, with the completion of the main construction work. According to Mehdi Rahmaoui, project director at TGCC, the first phase of the project, which includes technical lots and covering the western part of the stadium, is expected to be finished by the end of March 2027. This project is part of the preparations for the 2030 World Cup.

The construction site currently employs between 650 and 700 people working on multiple fronts to ensure the simultaneous execution of different operations and their coordination. The project began in June after the completion of excavation work following the demolition of the old stadium. The new stadium will have a capacity of 15,000 seats and involves interventions on the different structures of the stadium as well as on the spaces arranged underground.

The project consists of two phases, with the second phase focusing on the complete cladding of the new stadium. Rahmaoui did not specify the completion date for the second phase. The project aims to modernize the sports infrastructure in Fès and enhance its readiness to host matches for the 2030 World Cup. The first phase's progress is on schedule, according to Rahmaoui.

A recent site visit allowed media representatives to get firsthand information on the progress of the work, the ongoing interventions, and the next stages of realization of this sports infrastructure. This visit showcased the project's advancement and the efforts being made to meet the set deadlines. The project is being developed with a budget of over 2.8 billion MAD for the upgrade of the Fès stadium.

The construction of the Stade Hassan II is part of a larger plan to upgrade sports infrastructure in Morocco in preparation for the 2030 World Cup. The project includes several components, such as the renovation of existing stadiums and the construction of new ones. The goal is to ensure that Morocco's sports infrastructure meets international standards.

The 2030 World Cup is expected to have a significant impact on Morocco's sports sector and economy. The event will not only bring international attention to the country but also boost tourism and create new opportunities for economic growth. The construction of the Stade Hassan II in Fès is a key part of these preparations.

The project's progress reflects the efforts being made by Moroccan authorities to ensure the country's readiness to host the 2030 World Cup. With the completion of the main construction work by the end of November, the focus will shift to the second phase of the project, which includes the cladding of the stadium. The successful completion of the project will enhance Morocco's sports infrastructure and contribute to the country's economic growth.

Key points

  • The main construction work of Stade Hassan II in Fès is expected to be completed by the end of November.
  • The first phase of the project, including technical lots and covering the western part of the stadium, is expected to be finished by the end of March 2027.
  • The project aims to modernize the sports infrastructure in Fès and enhance its readiness to host matches for the 2030 World Cup.