Construction of the regional hospital in Tala, a delegation in Tunisia's Kasserine governorate, is scheduled to resume on November 19, 2026. The project had been stalled for almost a year but is now expected to continue over the next 12 months. This timeline should allow for the project's completion and handover by the end of 2027, with the hospital set to become operational in early 2028.

According to Abd al-Ghani al-Shabani, the regional health director in Kasserine, the issues that had delayed the project have been resolved. These issues included securing a reliable water supply and electricity, which were addressed through coordination with local and regional authorities, as well as with the National Water Exploitation and Distribution Company and the Tunisian Electricity and Gas Company.

The project to build the hospital was initially launched in January 2021, with an initial budget of approximately 53 million dinars funded by the Islamic Development Bank. The cost has since risen to around 57 million dinars. Once completed, the hospital will have a capacity for 105 beds and will offer various medical specialties and services.

Khalid Arnon, a member of the local development council in Tala, noted that the project's progress had been slow over the past two years, with only 45% of the work completed when the project was halted. He attributed the delay to the previous contractor's failure to meet their contractual obligations, leading to the contract's termination six months ago.

The local council in Tala has been working to address the challenges facing the project. They held a working session with the new contractor, attended by the mayor and technical and engineering officials, to review preparations for resuming work and resolving outstanding issues. The council continues to coordinate with various stakeholders to ensure the project's smooth progress.

The hospital is expected to provide essential healthcare services to residents of Tala and neighboring delegations, including Ayoun, Hidra, and Foussana. The project is seen as a significant development for the region, bringing healthcare services closer to citizens and improving patient care.

The resumption of work on the regional hospital in Tala marks a positive step towards enhancing healthcare infrastructure in the region. With a planned completion date in late 2027, the hospital is set to become a vital healthcare facility for the local community.

Key points

  • Construction of the Tala regional hospital is set to resume on November 19, 2026.
  • The project had been stalled for almost a year due to issues with water and electricity supplies.
  • The hospital is expected to be completed by the end of 2027 and become operational in early 2028.