The 5th steering committee meeting of the Project for Improving Connectivity in North-East Niger (PACNEN) was held on November 20, 2026, in Niger. Chaired by Minister of Equipment and Infrastructure, Colonel-major Salissou Mahaman Salissou, the meeting aimed to assess the project's progress and examine the implementation of the 2026 Annual Work Plan and Budget (PTBA 2026). The project focuses on improving the living conditions of Niger's population by enhancing socioeconomic infrastructure.

Minister Salissou highlighted that PACNEN has successfully coordinated the rehabilitation and maintenance of RN n°11 North, rural road development, and technical assistance for the operational implementation of these components. The project's primary objective is to improve the living conditions of communities along the corridor. He also appreciated the results achieved after five years of the project's existence, including 84.05% physical realization compared to the objectives set for the period 2021-2026.

The minister reported that 189.7 km out of 225.7 km have been rehabilitated, and 59.09% of the project's development objectives and intermediate results have been achieved. Additionally, the project has attained 96.25% of its financial realizations compared to the 2026 budget forecasts and 42.24% disbursement of the project's financing envelope. These results demonstrate the project's progress in improving infrastructure and living conditions.

The meeting examined the revised PTBA 2026 and the 2027 Annual Work Plan and Budget, prepared by the Technical Committee on October 13, 2026. The project's restructuring, which included an Additional Financing (AF) signed on June 9, 2025, and effective January 16, 2026, aims to rehabilitate 62 km of the Tiguidit-Agadez section and develop 200 km of rural roads. This restructuring has extended the project's intervention area to Niamey and Tahoua regions.

The project's objectives are to achieve 20.86% of the final goal of rehabilitating 287.7 km of roads, 21.54% of the final goal of developing 300 km of rural roads, and 23.11% of the project's total cost, equivalent to 34,878,164,762 FCFA. The minister emphasized the importance of synergy among committee members to achieve the predefined objectives and ensure the project's success.

Minister Salissou expressed gratitude to the authorities and committee members for their efforts in implementing projects that improve the population's well-being. He encouraged members to work together to accelerate processes and ensure that the project aligns with the government's vision and meets the population's needs and expectations.

The PACNEN project is a significant initiative aimed at improving socioeconomic infrastructure in Niger. The project's progress and future plans were discussed during the 5th steering committee meeting, which was chaired by Minister Salissou. The meeting's outcomes will contribute to the project's success and enhance the living conditions of Niger's population.

Key points

  • The 5th PACNEN steering committee meeting discussed progress and future plans for improving socioeconomic infrastructure along the RN11 North corridor in Niger.
  • The project has achieved significant results, including 84.05% physical realization and 96.25% financial realization compared to the 2026 budget forecasts.
  • The project's restructuring has extended its intervention area to Niamey and Tahoua regions, aiming to improve infrastructure and living conditions in these areas.