The 110 MWac Three W Solar farm, located in Hill County, Texas, has reached substantial completion and secured approval from the Electric Reliability Council of Texas (ERCOT) for grid connection. This marks a significant milestone for Mitsui, positioning the company to hand over operations. The project, situated on approximately 875 acres near Hillsboro, Texas, has a nameplate capacity of 150 MWdc or 110 MWac. This capacity is sufficient to supply electricity to around 45,000 homes.
The Three W Solar facility was developed by OCI Solar Power, which spent about two years preparing the site before selling the 110 MWac project to Mitsui in April 2023. At the time of the sale, OCI indicated that the project was construction-ready, with construction slated to start in 2024 and commercial operation targeted for 2025. Black & Veatch served as the engineering, procurement and construction (EPC) contractor for the project.
The EPC contractor completed the installation of solar racking piles, a generator step-up transformer and the collector substation before commissioning the facility. With construction now finished and ERCOT interconnection approved, the facility is set for final turnover to Mitsui's operations and maintenance organization. This move will bring the project toward commercial operation, enabling Mitsui to pursue wholesale power sales and direct supply to industrial customers.
Mitsui plans to leverage its U.S. energy-marketing subsidiary to market the power generated by the Three W Solar project. This aligns with the company's broader strategy to build an integrated power business in Texas. Industry trackers confirmed that the plant remained under construction in early 2026, listing Mitsui as the owner and noting the 110 MWac capacity.
The addition of the Three W Solar project contributes to the expanding utility-scale solar portfolio within the ERCOT market. While the project is smaller than some newly commissioned Texas solar farms, it complements other recent projects in the region. The completion of the Three W Solar facility demonstrates Mitsui's commitment to growing its renewable energy presence in the United States.
The project's development and construction involved collaboration between multiple parties, including OCI Solar Power, Black & Veatch and Mitsui. The successful completion of the project showcases the effectiveness of these partnerships in delivering large-scale renewable energy initiatives. As the demand for clean energy continues to grow, projects like the Three W Solar farm play a vital role in meeting this demand.
With the Three W Solar project nearing commercial operation, Mitsui is poised to make a significant impact in the Texas energy market. The company's focus on building an integrated power business in the state is expected to drive growth and innovation in the renewable energy sector. As the energy landscape continues to evolve, Mitsui's investment in the Three W Solar project positions the company for long-term success.
Key points
- Mitsui's 110 MWac Three W Solar Project in Texas has reached substantial completion and secured ERCOT grid approval.
- The project has a nameplate capacity of 150 MWdc or 110 MWac, sufficient to supply electricity to around 45,000 homes.
- Mitsui plans to leverage its U.S. energy-marketing subsidiary to market the power generated by the Three W Solar project.