Kenya Power has been criticized by members of the National Assembly's Departmental Committee on Energy and Petroleum for postponing the completion of Phase Four of the Last Mile Connectivity Project from October 2026 to June 2027. Committee Chairperson David Gikaria warned the utility to tighten procurement checks. He insisted that contractors must demonstrate both technical competence and financial capacity before being awarded tenders. This warning comes as lawmakers raised concerns about the selection of firms previously flagged for poor performance or debarred by development partners.

Lawmakers also questioned whether adequate due diligence was carried out in the selection of these firms. Nambale MP Geoffrey Mulanya highlighted the lack of consultation when connection sites were altered. He noted that residents had already been surveyed and their identification documents collected for the original locations. Mulanya cited a specific case in his constituency where a proposed connection point was removed without prior notice. This left households disappointed after expecting electricity supply.

Kenya Power explained that its request for the 2026/27 fiscal allocation was submitted in July 2026. However, Treasury approval only arrived in late October, delaying contractor payments. The utility also noted that an extension to the French Development Agency financing agreement was only secured on 18 November 2026. This temporarily halted VAT and import-duty exemptions for project materials at customs. As a result, the project faced significant delays.

To mitigate payment bottlenecks, Kenya Power opened a dedicated bank account for the 26 active EPC contracts. These contracts cover 17 EU-funded lots worth Sh17 billion and nine EIB-funded lots valued at Sh7.9 billion. The utility reported that Sh4.4 billion, representing 68 percent of the allocated disbursements, has already been paid through the dedicated account. This move aims to ensure smoother financial transactions and project implementation.

The committee reiterated its demand for stronger procurement oversight, better coordination with elected leaders, and clearer communication. These measures are necessary to avoid further delays in delivering electricity to targeted communities. The Last Mile Connectivity Project is crucial for increasing access to electricity in Kenya. Its delays have significant implications for the country's energy sector and economic development.

The project's delays have affected various communities across Kenya. Many households have been waiting for electricity connections, and the postponement of Phase Four has left them in limbo. The National Assembly's Departmental Committee on Energy and Petroleum will continue to monitor the project's progress. They expect Kenya Power to implement the recommended changes to ensure the project's timely completion.

Kenya Power must address the concerns raised by lawmakers and implement effective measures to prevent future delays. The utility's ability to deliver the Last Mile Connectivity Project on time will have a significant impact on Kenya's energy landscape. The project's success will depend on Kenya Power's procurement, funding, and communication strategies.

Key points

  • Lawmakers criticize Kenya Power over delays in the Last Mile Connectivity Project, now pushed to June 2027.
  • Committee demands stronger procurement oversight and better coordination with elected leaders.
  • Kenya Power opens dedicated bank account to mitigate payment bottlenecks.