Fenchurch Group has commenced the rehabilitation of the 26-megawatt Akute Independent Power Plant in Nigeria. The project aims to provide dedicated electricity to major Lagos waterworks. The first 10MW of power is expected to be delivered within four months. This initiative is being developed by Fenchurch Power Limited through Aggregate Utilities Limited, the group’s special purpose vehicle. The project is being delivered under a concession agreement with the Lagos State Government.

The 26MW Akute power plant will support the operation of the Akute intake, as well as the Iju and Adiyan waterworks. These waterworks rely heavily on electricity for water production. The remaining 16MW of power is expected to be delivered within 12 months. Surplus power generated will be exported to the Ikeja Electric network. This development is expected to enhance the reliability of water infrastructure in Lagos State.

Group Chief Executive Officer of Fenchurch Group, Olufemi Bakare, emphasized the importance of the project. He stated that the initiative was intended to keep the water infrastructure running reliably. Lagos State has invested significantly in its water infrastructure, and Fenchurch Group’s mandate is to ensure its continuous operation. The project will provide the necessary power to keep the water infrastructure running round the clock.

The equipment for the project is being prepared at the Oregun fabrication yard of Jubaili Bros. A stakeholder visit was conducted at the yard to assess the progress of the project. During the visit, Bakare highlighted the significance of the project in ensuring the reliable operation of Lagos State’s water infrastructure. The project is a collaboration between Fenchurch Group and the Lagos State Government.

Agiri Mustafa, Head of Production at Lagos Water Corporation, emphasized the crucial role of reliable electricity in water production. He stated that most of the corporation’s equipment is power-driven. The corporation will be the primary off-taker of the electricity generated when the equipment is installed. This partnership will ensure a stable power supply for water production.

The Akute power plant project is a significant development in Lagos State’s efforts to enhance its water infrastructure. The project will provide a dedicated power supply to the Akute intake and other major waterworks. This initiative will improve the reliability and efficiency of water production in the state. The Lagos State Government has been working to upgrade its water infrastructure.

The rehabilitation of the 26MW Akute power plant is expected to be completed in phases. The first phase will deliver 10MW of power within four months. The second phase will deliver the remaining 16MW within 12 months. The project will not only support water production but also contribute to the overall development of Lagos State’s infrastructure.

Key points

  • Fenchurch Group commences rehabilitation of 26MW Akute power plant to provide dedicated electricity to Lagos waterworks.
  • The project aims to deliver 10MW of power within four months and 16MW within 12 months.
  • The initiative will support the operation of Akute intake, Iju and Adiyan waterworks, and export surplus power to the Ikeja Electric network.

Share this story

Written by

SaharaWire Newsroom
SaharaWire

Reporting for SaharaWire from the Nairobi bureau.