The National Tunnels Authority in Egypt reported that work was temporarily disrupted at the Sand Tram site in Sidi Gaber, Alexandria, due to a slide of concrete blocks. The incident occurred on October 6, 2026, amid rainfall. According to the authority, their teams quickly responded to the situation, successfully lifting the displaced blocks and resuming work promptly.
An investigation into the incident revealed that the movement of some concrete blocks, stored by one of the executing companies, was triggered by the rain, leading to a limited landslide at the storage site. The authority confirmed that necessary actions would be taken against the company responsible for the blocks.
The National Tunnels Authority emphasized that the safety of citizens and workers, as well as the security of execution sites, is a top priority throughout the project's various stages. The authority assured continuous monitoring of work sites, particularly under varying weather conditions, and the implementation of preventive measures to ensure the work continues safely.
In response to the incident, the authority reinforced the importance of increasing safety and security measures at storage sites and all project execution sites. This move aims to prevent similar incidents from recurring. The authority remains committed to closely monitoring and coordinating with relevant parties throughout the project's execution.
The project to develop the Sand Tram is proceeding with ongoing field monitoring. The authority is working to ensure that the project adheres to technical standards and safety protocols. The incident highlighted the importance of stringent safety measures, especially under challenging weather conditions.
The National Tunnels Authority's swift response to the concrete block slide demonstrates its commitment to maintaining project timelines while prioritizing safety. The authority's proactive measures aim to mitigate risks associated with weather conditions and ensure the project's successful completion.
The Sand Tram project in Alexandria is a significant infrastructure development aimed at enhancing the city's transportation network. The project's progress is being closely watched by local residents, who anticipate improved mobility and connectivity. The National Tunnels Authority's efforts to address the recent incident and reinforce safety protocols are crucial to the project's success.
Key points
- The National Tunnels Authority responded quickly to a concrete block slide at the Sand Tram site in Sidi Gaber, Alexandria, ensuring work resumed promptly.
- The incident was attributed to the movement of blocks stored by an executing company, triggered by rainfall.
- The authority has taken and will take measures to enhance safety and prevent similar incidents in the future.