A 20,000-litre rainwater harvesting tank constructed at Kashambya Health Centre III in Rukiga District has not been put to use due to several defects. The tank was built in March 2026 by the International Crane Foundation, a non-governmental organisation that works with communities to protect wetlands and crested cranes. The project was implemented under the Ministry of Water and Environment with funding from the United Nations Development Programme and the Green Climate Fund. The tank was meant to provide water for health workers living nearby.

Authorities discovered several defects, including leaking walls and floors, poorly installed gutters and missing tap stands, which led to the refusal to commission the tank. Elineo Bandaganiire, the Kashambya Sub-county LCIII Chairperson, stated that the tank could not hold water, raising concerns about its durability. The design of the structure and poorly installed gutters meant to collect rainwater also raised concerns. Bandaganiire said the contractor was instructed to fix the defects, but no repairs have been carried out.

The continued failure to use the tank is worrying, according to Joram Niwagaba, the district councillor representing Kashambya Sub-county. The health facility needs better infrastructure, and district authorities had promised to intervene and ensure the defects were fixed. However, no action has been taken. Niwagaba's concerns echo those of the local community, who were looking forward to the tank providing them with a reliable source of water.

Rukiga District LC V Chairperson Simon Mutebi says the district leadership is aware of the problem. Mutebi stated that the original contractor hired another company to carry out the construction work. The district is waiting for the subcontractor to correct the defects before the tank can be commissioned. However, Mutebi argues that the district should not be held responsible for the construction defects because it was not directly involved in implementing the project.

A similar rainwater harvesting tank built at Kantare Secondary School in the same sub-county was successfully commissioned after it was found to have no defects. Bandaganiire used this example to highlight the differences in quality between the two projects. The successful commissioning of the Kantare Secondary School tank demonstrates that the construction defects at Kashambya Health Centre III are not inherent to the design or implementation of such projects.

The International Crane Foundation and the Ministry of Water and Environment have not commented on the issue. The United Nations Development Programme and the Green Climate Fund, which provided funding for the project, have also not made any statements. The lack of response from these organisations has left the local community and authorities frustrated.

The defective tank has left the health facility with limited access to water, affecting the delivery of healthcare services. The district leadership's inaction has raised concerns about the accountability of those involved in the project's implementation. The community is eagerly awaiting the resolution of the issue and the commissioning of the tank to provide a reliable source of water for the health workers and the local community.

Key points

  • The tank was constructed with funding from the United Nations Development Programme and the Green Climate Fund.
  • The defects include leaking walls and floors, poorly installed gutters and missing tap stands.
  • The district leadership is waiting for the subcontractor to correct the defects before the tank can be commissioned.